• Construction Update

    Posted by Justin Eckard on 9/9/2019

    Construction Schedule

     

    Phase 1 (classroom & administration suite) is on schedule

    Phase 1a (auxiliary gymnasium) is ahead of schedule – completion in February 2020

    Phase 3a (locker rooms) is complete

    Phase 4a (mechanical room) is on schedule

     

    Upcoming

    Phase 4b (kitchen/food court) will start in January 2020

     

    Comments (-1)
  • Facts About the High School Renovation Project

    Posted by Staunton City Schools on 2/11/2019 2:20:00 PM

    Stay current on the status of the high school project.

    Download our fact sheet to see the features of the future Staunton High School and get details on the project budget.

    an aerial view of the future Staunton High School

     

    Comments (-1)
  • Architect Presents Plans for Renovated High School

    Posted by Staunton City Schools on 11/13/2018

    new classroom wing Architect Josh Bower of Crabtree, Rohrbaugh & Associates in Charlottesville unveiled plans for a renovated high school at the School Board’s meeting on Nov. 12.


    The modernized school, which will feature more than 100,000 square feet of new construction, is scheduled to open in the fall of 2020.


    The project is scheduled to go out for bid in the spring, between March and April of 2019, and groundbreaking on the new classroom wing of the school is planned for late spring or early summer.


    The architecture firm is still working with the school division to finalize the design of the building, which is scheduled to be completed in the next couple of months.


    View renderings of the new and renovated building and a fly-around video of the school.